Hello All,

We are in to REM Scenario.

Issue is like this, when doing in-process inspection with inspection type 13, results recording is done. When we try to do UD for that inspection lot it is asking for the batch entry in the UD screen. This lot is retained for 2 weeks. This inspection lot contains so many batches and this is inprocess inspection. It should not ask for the entry why this is asking??

Material is batch managed and batch entry is given during the confirmation/MFBF (GR) of the quantities.

Please help in solving this issue..

Thanks in advance.

Regards,

Siva

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member42744
Active Contributor
0 Kudos

Yes.. you make a batch.. inspect... make a batch inspect..make a batch.. inspect..

So..

create inspection lot, provide batch number, make UD, create inspection lot, provide batch number, make UD

create inspection lot, provide batch number, make UD

create inspection lot, provide batch number, make UD

You are still making the inspection lots for the same production version.

See SAP help:

http://help.sap.com/erp2005_ehp_01/helpdata/en/be/00bbd8ca5311d2961800a0c930e04c/frameset.htm

Craig

former_member335796
Active Contributor
0 Kudos

Hi Craig,

Thanks a lot..

I will again look into the entire process and inform you for further suggestions..

Regards,

Siva