I am working on Project System for our department. We will be using SAP PS and Scheduler from Rockwell automation for dynamic tracking of materials on the shop floor.

Our Project will have the following WBS:

1) Design

2) Process Planning

3) Material Planning

4) Manufacturing

5) Assembly

6) Trial

7) Approval

😎 Dispatch.

Of the above 8 WBS, manufacturing activities will be scheduled and tracked through Scheduler instead of SAP PS.

How can the data from scheduler transferred to PS so that thw cost of each work center gets attached to the project?

Is it possible to transfer the data to PP module from scheduler instead of PS and still the cost gets attached to the project?

OR

Can PS be used for dynamic tracking and if yes please tell me how to go about it?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi John,

In my opinion, you should use BAPI to transfer data. Both PP and PS BAPIs are available, you may select relevant to your use. It seems you want to create PS activities and update their schedule. In this case refer documentation of BAPI_PROJECT_MAINTAIN in tcode SE37. BAPI_NETWORK_CONF_ADD will help to confirm activities.

Regards

Answers (0)