SAP has to be implemented at my client side and they take customer project.
For giving quotation, are sales order generated for creation of projects?
If yes, then how do we plan the costs for project? Does this sales order take costs from project or vice-versa?
Edited by: Pallavi Choudhary on Jun 3, 2008 1:16 PM
Edited by: Pallavi Choudhary on Jun 3, 2008 1:27 PM
With the assembly process, you generate the network and the project from the cuotation.
The cuotation gets the planned cost from the network asigned to the sales document position, you need a planing profile for the network and define the strategy to determine the price of the material you need.
You will need to assign materials to the standar network and the workcenter with the activity and time it needs.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.