GRN is not possible ...

Former Member
0 Kudos

Hi Friends

I am getting an error while doing a GRN. When i do GRN by taking a reference of PO an error comes :

" goods reciept for purch. order" is not allowed(WBS XXXX.XXX.X)

I have checked system as well as user status and both allow the business transaction .Pls let me know what can be the exact reason , a quick reply will be highly appreciated.

thanks in advance....

Vikram

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check whether you can maintain stock for WBS. Goto CJ20N, open you project, on 'Control Data' tab page check what is maintained under Project Stock section. I doubt it is no stock.

Regards

Former Member
0 Kudos

Hi

I have checked it is "valuated stock"...

For more clearification below is given the description of error:

"Goods receipt for purch. order" is not allowed (WBS PS.0002.1.B.02.A)

Message no. BS007

Diagnosis

The current status of object 'WBS PS.0002.1.B.02.A' prohibits business transaction 'Goods receipt for purch. order'.

Procedure

To process business transaction 'Goods receipt for purch. order', you first have to change the status of object 'WBS PS.0002.1.B.02.A' to allow the transaction 'Goods receipt for purch. order'.

This gives you an overview of the system and user statuses that affect the transaction. A transaction can only be executed if there is at least one status that allows it and there is no status that forbids it.

But i have already checked that neither system status nor user status disallow the business transaction.

Former Member
0 Kudos

Hi,

It definitely appears to be status issue, please let me know the status of WBS.

Regards

Former Member
0 Kudos

Hi

the system status is PREL & BUDG

User status is REL , the user staus doesn't restrict the business transaction "GR for PO"

waiting for further suggestion...

Former Member
0 Kudos

Your user status seems to be prohibiting the GR process. Set the status suitably (after talking to person who configured it)

Regards

Sreenivas

varshal_kachole3
Active Contributor
0 Kudos

Hi,

It seems you have only released the activity.

Please release the WBS element in question.

That will soleve your issue.

hope its useful.

Reward points if useful.

thanks..

Former Member
0 Kudos

Hi Varshal

WBSE and activity both are already released...

regards

Former Member
0 Kudos

Try releasing all the lower level WBS elements under this higher level WBS. Ensure to have status REL on the WBS against which you are doing the GR.

Regards

Sreenivas

varshal_kachole3
Active Contributor
0 Kudos

Hi,

I am assuming the status of WBS PS.0002.1.B.02.A as PREL,BUDG.

PREL meaning it is partially release.

Please select this WBS PS.0002.1.B.02.A in CJ20N and go to EDIT->Status-> Release.

After this save the project.

Open the same project the status of the WBS PS.0002.1.B.02.A should be REL BUDG

Now Try the GRN.

Hope its sueful.

Reward points if useful.

Thanks..