Automatically update Cost plan for changes in standard cost ?

Former Member
0 Kudos

Is it possible to Automatically update Cost plan for changes in standard cost ?

My standard cost is maintained in material master data for example.

After project is created and item is not yet delivered, if my standard cost changes ... how can i update

my cost plan ?

help is appreciated.

-San

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Refer similar thread:

Answers (1)

Answers (1)

Former Member
0 Kudos

Please check OPUV

In Plan Cost Calc. Select 4 - Update Planned costs