on 06-02-2008 4:47 PM
Folks I have been reviewing Billing Plans, both Periodic and Milestone, and nither seem to be able to help me out.
I have a very simple request from my customer and can not believe SAP has no option for it (as far as I can determine).
We want to sell an item (XYZ) to the customer, then deliver it, then have 6 or 9 or 12 equal monthly bills generated and sent to the customer.
Example: - Item XYZ sale price is $60,000. Sales order created for 1 item.
- Delivery complete and posted (shipped) to customer.
- That night (after the delivery is complete), we create/send first invoice for $10,000.
- The subsequent 5 invoices for $10,000 each will be sent on the monthly anniversery date of the
delivery.
We also have requirements for something like 20% down and the remainder paid off in 9 or 12 monthly installements, but I believe I can review the down payment information in configuration.
I am not really a configurator, just an ABAP'er (the only one). We have no configurators here at my company, so please bear with me on this issue.
Thanks.
No longer needed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not quite sure why milestone billing plan does not satisfy your needs. In there you can simply enter dates and values and then, providing your billing due list is set for order-related billing, the invoices will be generated as required.
Regards,
Brian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Again, the one problem I am having is that when you enter in material on line item 10 of a new Sales Order, then double click in the line item to get to the "Bill Plan" item tab, then click on the "Bill Plan" tab, a POP-UP window displays asking for a NETWORK number or a WBS Element.
We do not have Project Systems set up here at my company, so we do not use NETWORK or WBS Elements.
I can get by the little pop-up screen, by clicking the red "X" and I can enter in dates and percentages on the Billing Plan tab, but when I look at the "AZWR" Pricing Condition it is $0.00 and only the PR00 condition has a dollar value. Should I only see the AZWR pricing condition in the Conditions tab or should the PR00 show the Sale Item's value (say $40,000) and the AZWR condition show what we want for a down payment (say $10,000)?
Hi scott
You can make this using down payment configurations in SAP
please go through the configurations of down payment
Make the following down payment configurations
item category group - 0005
item category - TAO
for this TAO item category a billing plan 01 (milestone billing plan -01) will be assigned and its billing relevance should be I which is order related billing .
billing doc type - FAZ
cancellation billing doc type - FAS
maintain a condition type AZWR which is down payment settlement , it has requirement as 2 and calc type as 48 acct key as ERL
Now when you enter a material in line item 10 and go to item data , you can see the billing plan tab.
now go to billing plan tab and enter the start date and enter the dates on which billing has to be done and then in billing request enter 0009 which is for down payment.once u press enter automatically it all the dates get blocked and billing request by default you get as 1 , that you change it to 4 or 5 . 4 is for down payment at value basis and 5 is for down payment at percentage basis. and beside that there will be a billing type .assign billing doc type as FAZ. to all dates
check the copying requirements are there at VTFA as 20 and for item category TAO copying requirements 23 is maintained or not
now do the cycle OR - LF - FAZ (billing doc type)
Now in your case enter 50% of the net value automatically the remaining amount will get calculated
Regards
Srinath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi scott
AZWR is the standard condition type which is available in SAP and there is no need to copy . from PR00 like that . Just as you assign PR00 condition type in your pricing procedure , in the same way assign AZWR condition type in the same pricing procedure .It has reqt 2 and alt calc type 48
Regards
Srinath
I have done the configuration you stated, now when I create a sales order and enter in the material and quantity on line 10 and try to go to the Header (or detail line) Bill Plan tab, a pop-up screen asking for either a Milestone parameter or a WBS Element is displayed.
We have neither here at my company.
We just want to see the Bill Plan screen where we can enter in the dates and amounts of the monthly payments.
Scott.
Dear Scott
You can try with this option.
Go to OBB8, select the box "Instalment Payment". Next go to OBB9 and maintain different payment terms and maintain instalments accordingly. Now you maintain these payment terms in sale order
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I tried what you suggested (from one of your ealier posts to another person who had a similar problem as mine).
I created a Payment term with just the "Installment Payment" flag turned on (IP06)
Then via OBB9 I created 6 entries:
Payment Terms Inst. Percentage Pymt Term
IP06 1 16.67 NT00 (NT00 is defined as due immediate)
IP06 2 16.67 NT30
IP06 3 16.67 NT60
IP06 4 16.67 NT90
IP06 5 16.67 NT12 (NT12 is 120 days)
IP06 6 16.67 NT15 (NT15 is 150 days).
But when I created the Order, delivered it, and ran VF04 and generated the first bill, the entire amount ($60,000) was invoiced.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.