The below requirement is for one of our clients project.
Generally in their business, All External service contracts are created as Framework orders in SAP. These Framework orders are attached to PM(Plant maintenance) work orders as of now for Ordering External services. 'Framework Order' field is present in Operations External tab of PM Work Order.
The Requirement is to link the above Framework orders to PS Network activities as well. I couldnt find a field 'Framework order' present in External tab of Network activity. How the link is possible?? Is it possible through standard config settings???
Quick response is appreciated.
Thankyou.
Regards,
Karthik
Hello,
In the specific PM order goto "Additional Data" tab page and input the PS Network-Activity number.
This would associate the particular PM order the specifice PS Nework Activity.
Thanks
Anish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In the Project system, for the external activity.
On enternal tab there is a field "Outline Aggrement".
this you can use for the desired purpose.
thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Karthik
I understand that you can not have frame work orders in PS similar to PM.
Let's see others views on this.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.