Former Member
0 Kudos

Hi,

The scenario of my client is that -

my client is in Project system while doing sales order he is mentionning whole project cost e.g CNC machine kit in which many materials are there.while dispatching he is making partial delivery of materials

my question is -

how to map this in SAP because while doing partial deliveries we do scheduling in sales order but in this case my sales order is of complete unit so how to map??

Regards,

rahul

Points will be reward

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi

i think this can be done using the concept of BOM's

in your case ur CNC machine is the finished product ( main material)

and create the sub materials

using CS01 create BOm

and you can have Complete and partial deliveries in BOM also

all the best

regards

ravi

varshal_kachole3
Active Contributor
0 Kudos

Hi,

In your case the CNC Machine will be the project.

So create the material master for CNC Machine as FERT material which is billable. And create Sales order with Item category TP01 standard.

Now create a project for this sales order. And assign all the other components inside the project which will be delivered (HALB).

Now once this material is available in the project stock create the delivery from project.

Hope its useful.

Reward points if useful.

Former Member
0 Kudos

Hi,

[Partial Delivery and Complete Delivery |http://help.sap.com/erp2005_ehp_03/helpdata/EN/dd/5607f4545a11d1a7020000e829fd11/frameset.htm]

[Delivery from Projects|http://help.sap.com/erp2005_ehp_03/helpdata/EN/4c/227cdc46e611d189470000e829fbbd/frameset.htm]

Assign Points if helpful.

Thanks and Regards,

Naveen Dasari.