Hi

We have done File to IDOC Scenario succesfully i.e HR

data from file has been mapped to HR Idoc(HRMD_A06) .

Now when Idoc is posted to R/3 , SXMB_MONI shows

successful status(Idoc posted successfully) .

But when we check in R/3 in WE05 transaction ,though

the idoc is present but it shows status 51/52

with message "Idoc could not be posted" /"IDOC not

fully posted" .

In this case how can we track in XI whether the Idoc

is properly posted in the target system(i.e R/3) .

Since XI only shows that Idoc was successfully sent

irrespective of the status in R/3 .

Please suggest as we are new to XI .

Regards,

Shikha

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Thanks for the guide.

we are not sure of the steps to configure it in R/3

system so that it sends the acknowledgement back to XI

system.

When we tried to configure it as per the guide , for

test purposes we executed the program RBDSTATE but it

gave message "No parties are interested in the selected

data" .

Please guide us on this .

Thanks

Shikha

Message was edited by: Shikha Jain

Former Member
0 Kudos

Hi Shikha,

You have to setup the ALEAUD01 IDOC to be sent back from the target system. This way the status of the IDOC message sent from XI will be updated with the status coming back from the Target System.

Check this document.....

http://sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/xi/xi-how-to-guides/how to handle acknowledgments for idoc.pdf

Thanks & Regrads,

Renjith

Former Member
0 Kudos

Shikha,

I don't think you will be able to do that. However, I am just wondering, once you send the data successfully wouldn't it be the problem of the R/3 guys to see if the IDOC is being posted successfully.

Regards,

Ravi