MRP run

Former Member
0 Kudos

Pls. tell me..can we do MRP run more than once for any project?

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Yes you can do that,

Whenever there are any changes in the material component quantity in the BOM, you can run the MRP, Provided the PRs are not converted to POs.

Hope its useful.

Reward points if useful.

Thanks..

Former Member
0 Kudos

What will happen if PRs had been changed to PO?

Do we perform MRP run for Project, not for WBSEs or activities?

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Assume initally the requirement was 10 no. MRP was run, PO was created.

Scenario 1: BOM was modified to 8. MRP was Run, no change in PR and PO quantity. Still 10 Would be in the PO

Scenario2: BOM was modified to 12, PRs will be created for the additional 2 requirement.

Hope its useful.

Reward points if useful.

Thanks..