Not able to connect to the central XI Integration Engine

Former Member
0 Kudos

I have configured the ABAP Proxy and have atcivated all the steps in the configuration but still not able to connect to the central XI Integration Engine. What could be the possible cause of it?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please check if the host names entered in the Exchange profile are able to be resolved from the business system ( the SAP server >640 ).

If the host names are not resolved then the HTTP communication will not work and SPROXY -> Goto -> Test Connection will report failure on SPROX_CHECK_IFR_RESPONSE, SPROX_CHECK_IFR_CONNECTION

Thanks

Swarup