when i am releasing a billing document to accounting...this error is coming...

"Account 40013000 requires an assignment to a CO object"

what has to be done...can you give me any steps please

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

Goto the TCODE KA01 enter the controlling area ,

give the Gl acoount No ,

click on Master data tab ,

when u entered into the detailed screen check Default Acc Assgmnt key and enter Cost centr and save.

Answers (2)

Answers (2)

Lakshmipathi
Active Contributor
0 Kudos

If 40013000 is a revenue element , account needs a profit center. If it is a cost element , then account needs a cost center.

thanks

G. Lakshmipathi

former_member204513
Active Contributor
0 Kudos

Hi Sap sd,

Take help from FI people they will be able to do it

Regards,

Murali.