on 05-29-2008 5:29 PM
Hello,
I would like to know under what circumstances, which Strategy groups are used in MRP2 screen of Material Master. We use Strategy group # 85 to trigger creation of Operative Network and Project when Sales order is created in system for Assembly processing. We are in roofing industry for every roof installation, we create sales order. We don't use Networks but use Projects W(with 2 wbs elements) to capture Planned and Actual Revernue and Costs. If possible, I would like to know with real world scenarios for various Strategy groups used.
Following are the various Strategy groups available in system.
00 No planning / no requirements transfer
10 Make-to-stock production
11 Make-to-stock prod./gross reqmts plnning
20 Make-to-order production
21 Make-to-order prod./ project settlement
25 Make-to-order for configurable material
26 Make-to-order for material variant
30 Production by lot size
31 Prod. by lot, with make-to-order prod.
32 Make-to-order prod. with prod. by lot
33 Prod.by lot, with plng with final assem.
40 Planning with final assembly
41 Plng with final assem, with make-to-ord.
50 Planning without final assembly
51 Plng w/o final assembly / project settl.
52 Plnng w/o final assem. w/o make-to.stock
54 Planning variants
55 Planning variants w/o final assembly
56 Characteristics planning
59 Planning at phantom assembly level
60 Planning with planning material
61 Plng with plng material / project settl.
63 Planning w.plng material w/o mke-to-ord.
65 Planning variants with planning material
70 Planning at assembly level
74 Plng at assembly lvl w/o final assembly
80 Project settlement for non-stock items
81 Assembly processing with planned orders
82 Assembly processing w. production orders
83 Assembly processing with networks
84 Service orders
85 Assembly processing with network/project
86 Assembly processing with process orders
89 Assembly proc. w. characteristics plng
For project type of business ie Engineered to Order scenario wherein material is produced as per the Order and may vary from oorder to oredr- In this case strategy group 21 is used for Finished product(FERT).
In the above scenario requirements are generated using project MRP.
For make to order scenario where PS is not used and material is made using Production planning(prod order)-in this case strategy group 20 is is used for Finished product(FERT).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.