Adding column to tables that list tasks

Former Member
0 Kudos

Hello,

We have a request to add a column to some specific tables that display in cProjects. Would anyone know of a BAdi that would allow us to do this? We want to avoid making serious modifications and hope there is some sort of entry point that will allow us to make the addition within what the system will allow.

Tables 1 & 2: Predecessors, Successors

1) Open a project.

2) Click on a task.

3) Click "Relationships" tab.

Predecessors and Successors tables list task name. We would like to add a column to display the parent task (summary task) name.

Table 3: Tasks Assigned to Selected Project Roles

1) Open a project.

2) Click "Resources" tab.

3) Click "Tasks" tab.

Tasks Assigned to Selected Project Role table shows "Task" column. Again, we would like to add a column to display the parent task (summary task) name.

Any ideas?

Thank you,

Wendy Miller

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Business would still be interested in solution options for this.