How to check who has changed the system status of WBS

Former Member
0 Kudos

Hi All,

How to track that which user has changed the system status of WBS element in the Project?

One of my project has been Released and then made Deletion flag.

Now we are unable to remove the deletion flag...

Atleast i would like to know who has done this change...!!!!!

Kindly let me know......

Regards

PAvan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In the administration Data tab of the WBS, field 'Last Changed' should tell you who has changed it last.

If you need further details you might need to activate 'Change Document' a mentioned below:

Enable the 'Change Documents' at the project profile level and use/set a user status on the WBS to allow the business transaction 'Create change documents'. Use CN60 to view the changes.

Regards

Sreenivas

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Run the Tcode: AUT10 for the Tcode like CJ20N and CN80.

hope its useful.

Reward points if useful,