on 05-28-2008 1:06 PM
Hi, all guru
I'm new to SNP, would like to clarify the process flow .
What is the output of each SNP process after release the forecast from DP to SNP
1. is the first process is DRP ? when we run optimizer, what is the output , any order send to R3
2. how about Deployment and TLB run , any output , any order type created ? any data sent to R3
3. when R/3 received those data , what R/3 do with it .
4 what is the flow between SNP and MM/PP at R3
5. what is Rough cut capacity planning , it is seperate data being load to SNP, how to relate to SNP process
it will be very helpful if we can have a scenario base of example
many thanks
Hi :
following are the steps :
Once the demand plan is released form DP to SNP , Planned Independent Requirements are created for SNP / PPDS.
Now performing SNP Runs through Heuristics , CTM or Optimizer Results in Distribution & Production Plan for
Medium to long term horizon . After SNP run you can generate alerts for any exception and resolve them .
SNP plan now consist of Transaction data (Purchase requisition , SNP Stock transfer order or SNP Planned order) . If you are using PPDS , SNP orders can be converted to PPDS orders which are more detailed .
After production planning is complete , Deployment confirms stock transfer order based on current receipts and demand .
TLB runs groups together stock transfer orders into shipments .
All these transaction data is passed to R/3 through CIF .
SNP planning is rough cut only if you are utilizing SNP PPM which only contains critical resources and material .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.