cancel
Showing results for 
Search instead for 
Did you mean: 

Plant for PR in case of Centralized planning plant

0 Kudos

Dear All,

In case of centralized planning, if a Service PR is created then it is taking the plant as the planning plant & not the maintenance plant.

For example: Maintenance pLant A & Maintenance Plant B have a common planning plant as "A" & if a PR is created for maintenance plant "B" then it is taking the plant as "A" & not the other.

please suggest where we can change the plant in case of service pr created through the maintenance order.

Regards,

Ritesh

Accepted Solutions (0)

Answers (1)

Answers (1)

paul_meehan
Advisor
Advisor
0 Kudos

Hi,

The planning plant will always be passed to the purchase requisition as you have found. Only alternative is to use a user exit

For components use exit COZF0002 (EXIT_SAPLCOZF_002). The exit is called on creating purchase requisitions for components from PM/CS orders. Customer exit COZF0001 can be used for external operations.

This exit allows change of fields in structure EBAN_ORD_CUST. Field WERKS is not included in this structure but you can append this field to the structure. After that you have to add a line into your exit (example):

... move afvgd-werks to EBAN_ORD_CUST-WERKS...

Through this method it should be possible to change the plant on the requisition.

-Paul

Use the forum Enterprise Asset Management (EAM) for PM/CS specific topics