error in operation level result recording

former_member677849
Participant
0 Kudos

Hi,

I need held; result recording of inspection type =03 (operation level Quality inspection)

A product manufacture via three operations (10, 20, 30)

All operation quality inspection active let operation no-10, all products reject and confirm as rework.

Next operation level quality record is done but confirmation not allow Reason is operation -10, rework quantity, (Actual quantity is more than planned quantity)

How to add the quantity after reworks for next operation quality inspection?

Pl helps me finding the solution.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member677849
Participant
0 Kudos

ok

Former Member
0 Kudos

Dear Rajesh,

Yr question is not clear to me. pls elobrate more!!!!!

Regards,

Shyamal

former_member677849
Participant
0 Kudos

Hi,

As per your more clearence , As per Example production order Quanity =1, passes 3 operation10,20,30

Operation=10 require rework as per quality ,

Operation =20 system raise the error message = Operation =10 rework .

If want to operation =10 ok Quantity =1 then system raise error messges =Actual quanity more than planned Quanitity

( 1 Rework + 1 Ok ) .

Supose rework order create and confirm then next 20 & 30 operation how complete .

Real scenerio :- Rework on operation =10 then again Quality check then goes to 20 operation Quality check pass / Rework if rework then again quality pass then goes to next operation level

I hope under stand my problem

Need help- please

hanamanth_honyal
Participant
0 Kudos

Dear Rajesh Tiwari,

Go to QE02, then in the menu

Go to edit--> Correst actual quantity

Regards

Hanamanta

Former Member
0 Kudos

Hi rajesh,

In ur case u must be using rework order for operation.

Then in this case if all quantities get rejected in the very first operation for production order then how u can confirm the quantity against the same order?because this order is finished.U can confirm the quantity against the rework order only and difine operation 10 ,20, 30 there

So better way is to create rework operation then rework order

u can easily confirm rework qty against the same order and all quantity will get carry forward for next operation

Amol