PO Item not getting Deleted which is Assigned to WBS Element.

stheurkar
Active Contributor
0 Kudos

Dear All,

We have created one PO. In that total item are 490, so I have to delete item no 447.

For deleting item no.447 from PO, Firstly i have selected that item & clicked on Delete button.Before saving I am clicking on check button then system gives following error message.

Item 447 WBS element G.0720665.ME.PR.01 budget exceeded

Message no. BP604

Diagnosis

In document item 447 WBS element G.0720665.ME.PR.01, budget for fiscal year 2008 was exceeded by 59.840,00 INR.

Budget is also

How to go about from this issue.

Regards,

sandeep theurkar

Accepted Solutions (0)

Answers (2)

Answers (2)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Is MIGO done for this material?

If not then try this:

Step 1: Tcode CJBW

Step 2: Delete the line item from PO.

Step3. Tcode CJBV

Dont forget step3 in the end.

hope its useful.

Reward points if useful.

Thanks..

stheurkar
Active Contributor
0 Kudos

Thanks for Solution.

But this is the Right or Legal way to Delete PO item.

As you suggested 1st we have to deactivate availability control for projects, then delete po item & save.After this again we have to activate Project availability control.

By doing this way can i face any kind of problem from my management.

Is any other way to delete po item.

Points is Rewarded.

Thanks & Regards,

Sandeep N.Theurkar

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Try doing this:

go to this particular PO line Item which you want to delete.

In the net price, reduce it to 0.01 And now try to put the deletion inidcator.

hope it helps,

Reward points if useful. Revert back if any other issue.

thanks..

Former Member
0 Kudos

I think you have already created Purchasr requistions on this WBS element G.0720665.ME.PR.01.

Pls. check if any find then delete it or release the budget 59.840,00 INR on WBS.

Reward points if useful. Revert back if any other issue.

Regards,

Vishal Kr. Sharma

stheurkar
Active Contributor
0 Kudos

You can refer Budget details which i have taken from S_ALR_87013558 Report.

By using these details pls tell me how i can resolve the issue.

Total of years (In Rs.)

Budget Actual Commitment RemOrdPlan Assigned Available

  • * * * * *

467.500.000,00 221.426.653,23 246.051.400,91 467.478.054,14 21.945,86

467.500.000,00 221.426.653,23 246.051.400,91 467.478.054,14 21.945,86

Previous years (In Rs.)

Budget Actual Commitment RemOrdPlan Assigned Available

  • * * * * *

20.865,10 20.865,10 20.865,10

20.865,10 20.865,10 20.865,10

For the Year 2009 (In Rs.)

Budget Actual Commitment RemOrdPlan Assigned Available

  • * * * * *

467.479.134,90 221.405.788,13 246.051.400,91 467.457.189,04 21.945,86

467.479.134,90 221.405.788,13 246.051.400,91 467.457.189,04 21.945,86

Thanks & Regard's

Sandeep Theurkar