on 05-28-2008 10:53 AM
Hi Experts --
I made a sales order for a material then I check the stock requirment from MD04 and from MMBE I decide to plan for procurment .
I run the MRP then make a Pland Order f and assigning this Planed Oredr to a WBS with account assignment Cat. Q.
Then I am converting Planed Order to Thir Party Requistion .. from MD14 .when i save this I found a PR number
is there any way by which I can see the PR number in PS Module (to which I have convert in PR from Planed Order)
How can I see this material in Project Planning Board....
Please Clear the Concept .......
how can i see the PR in sales order too
thanks in advance
Regards
SMITH
is there any way by which this will show in Project builder with material assignment to activity--
and this requistion will show agains the componenet .
This is very urgent please clear this
Thanks in advance
Regards
SMITH
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
ME5J will give the lsit of all the PRs for the project.
Thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.