PR from Sales Order - Display the Number in PS?

Former Member
0 Kudos

Hi Experts --

I made a sales order for a material then I check the stock requirment from MD04 and from MMBE I decide to plan for procurment .

I run the MRP then make a Pland Order f and assigning this Planed Oredr to a WBS with account assignment Cat. Q.

Then I am converting Planed Order to Thir Party Requistion .. from MD14 .when i save this I found a PR number

is there any way by which I can see the PR number in PS Module (to which I have convert in PR from Planed Order)

How can I see this material in Project Planning Board....

Please Clear the Concept .......

how can i see the PR in sales order too

thanks in advance

Regards

SMITH

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

is there any way by which this will show in Project builder with material assignment to activity--

and this requistion will show agains the componenet .

This is very urgent please clear this

Thanks in advance

Regards

SMITH

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Select the particular material component in CJ20N, on the purchasing data tab one can see the PR number exactly at the top of the left hand corner.

hope its useful.

Thanks..

varshal_kachole3
Active Contributor
0 Kudos

Hi,

ME5J will give the lsit of all the PRs for the project.