I need to create delivery for project stock, but I'm not able to create PGI for that.

It has project stock in the inventory, but system only check the normal stock, and telling not enough stock for PGI.

What I need to maintain in SO and Delivery in order to let the system knows this is a project stock order? I've maintained the WBS element in SO's account assignment already.

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

check the storage location while creating the Delivery.

Send the message number.

hope its useful.

thanks..