When I create shopping cart and press the check pushbutton, I get the following errors
1. No commitment item assigned to G/L account 1000/400000, or assignment not valid
2.No commitment item entered in item 00001 1000 400000 (Item EXHAUST PIPE )
Please note the G/L = 400000.
controlling area = 1000
Could please guide 1. why is the error coming for the item 00001
and 2. sugest some remedy ?
Thanks and regards
Sachin
Hi,
I think this message comes from the R/3 system, it is a lack of customizing for MM/CO integration.
Ask you the functional team in charge of your R/3 system MM/CO customizing (you can try to create directly in R/3 a PO with the same data, you should get the error)
Regards.
Vadim
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Refer to this link ->
http://help.sap.com/saphelp_srm50/helpdata/en/82/cf7b3c5dc1b160e10000000a114084/frameset.htm
Try to either delete / change the message type from sRM system from ALE settings
Commitment Posting BBPCO
Please refer to these OSS notes as well.
<u>Note 1010702 - Commitment item ... does not exist
Note 845608 - Message texts from the back end are incomplete</u>
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
We have faced similar issue, some time back. We were using SRM 5.5 version at that time.
<b>I recommend, first try to implement this SAP OSS note. Incase it does not help, then try deleting the Message type - BBPCO.</b>
We applied this OSS Note.
Note 786854 - Modification note in order to deactivate commitments
Other related links ->
Hope this will help.
Please reward suitable points.
Regards
- Atul
Hi Atul,
Thanks for all your repllies.
The OSS note has less patch level than what we are using so I cannot implement it in our system.
I deleted BBPCO--- Commitment posting but unfortunately, the error still exists as same.
Does this issue belong to SRM or FI.
Any further thoughts please?
Reg.,
Sridhar.
Hi
Which SRM version are you using ? Are you using Budgeting in SRM Scenario ?
Please refer to these SAP OSS Notes as well.
<u>Note 828231 - Commitments and SRM
Note 524670 - Budget display in EBP
Note 900825 - Shopping cart commitment
633107 - EBP FM budget display
520717 - Budget check in EBP
695094 EBP error in Funds Management update
759489 Budget display for limit shopping carts and blanket PO
815354 Incorrect values in the budget overview
789275 Limit: Expected value is not filled
705557 No commitment update for deleted purchase orders
667632 No budget check in limit shopping cart
524670 Budget display in EBP
639903 Multicurrency-availability in budget display
526061 Error in budget availability check in shopping cart
68366 - Active Availability Control for Cost Centers
Note 47992 - No commitment is displayed in reporting
551506 - FAQ note Overhead Cost Controlling
520717 - Budget check in EBP
498907 - No commitment for valuated project stock
496784 - No commitment for purchase requisitions during the MRP
397799 - INFORMATION: CO-OM-OPA (Order & Project Accounting)
397239 - INFO:CO-OM Interface/actual postings/commitment/down payment
152571 - Composite SAP note: Missing or incorrect commitments</u>
Do let me know, incase still face any issues.
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This error comes due to an FI Customization issue.
Commitment is entered in T-Code "fs00". If this is not entered for the corresponding A/c to which the posting is done, you'll get this error.
Ask the FI func to set the Commitment entry for the A/c to which posting has to be done.