HI All,

Which Network type and settlement profile i will use so that i can settle network costs(Labor costs,material costs and serice costs) to the repective attached WBSE automatically while am settling the WBSE to the final reciver.

Muzamil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Network type PS02, settlement profile 130001 as per IDES will address your requirement. Basically check the following:

1. Network type contains the settlement profile which allows settlement to WBS (OPSC)

2. Parameters for network type have default rule PS1 ie 'settlemt to WBS' (OPUV)

Regards

Former Member
0 Kudos

Hi Srikanth,

Thanks.IN OPUV Under stragey what i have to put.

My scanario is to to settle Acct & billing WBS elements to GL only ...

Muzamil

Former Member
0 Kudos

Hi Muzamil,

You can maintain 01: to WBS/Proj Defn

Regards