hi ps experts,

pl help in let me know how to customise value category in ps.

thanx & regards

Srihari

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

Also refer ...

SAP Note: 676123.

Hope this helps.

Venkat

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

To begin with:

We need atleast 4 Value categories:

1. Tcode: OPI1

Maintain 4 value categories e.g. 1300,1301,1302,400 and 410

For 1300, 1301, 1302 Select statistical key figure with total values.

For 400 select Costs.

For 410 Select Revenues.

2. Tcode KAH2: Create Cost element Groups.

e.g PSCost: assigne all the cost relvent cost elements to this group

PSREV: Assign all the revenue relevent cost elements to this group (Cost element category:11)

Step:3 Tcode:OPI2.

Assign PScost to 400

Assigne PSRev to 410

3. Tcode CJVC, Check consistency for the value categoy assignments

4.Tcode KK01: Create statistical Key figure. e.g 10, 20,30 for the Controlling area.

5. Tcode OPI5:

Assign these 10,20,30 to 1300,1301,1302 respectively.

For detailed discussion on this topic please refer:

http://help.sap.com/saphelp_46c/helpdata/en/3d/72369adc56d11195100060b03c6b76/frameset.htm

Hope its useful.

Reward points if useful.

Thanks..

former_member221039
Active Participant
0 Kudos

hi

I have customised the value category customising as suggested for only costs.

With this customisation, can i get individual values of project network external processing in cn41 report.

currently cn41 report, external processing header is only showing total value of materials planned.

I wud like to have values of individual line items of materials or services as per the PR in cn41.

Please let us know how i can see the individual line items costs ( planned or actual) in cn41 for materials & services.

pl help

regards

srihari