Actual Costs in Internal Order and WBS

Former Member
0 Kudos

Dear All,

I have configured Accounting Integration with cprojects successfully for both Internal Order and Multi-level controlling. I need your help in entering the actual costs occured for the project execution.

I am using Task based costing.

One more things is how to enter the additional costs in project execution other than resource or task costs in both planning and actual costs. I think in planning we can enter the additional costs in Easy cost planning.

regards,

rajesh.

Edited by: Rajesh Madala on May 27, 2008 10:59 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rajesh,

As you say, additional costs can be entered through Easy Cost Planning, just by selecting the desired element and adding new row with the cost data.

Neil