There is usually insufficient stock for the orders and proıduction is needed for the orders (make to order). We have a material of A and there exist its components X as raw material and W as semi finished material. We want the availability check to take into consideration not only the material itself but also the components (raw materails, semi-finished products). How can we customize about this case?

Thanks in advance...

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please check:

SPRO-> SD->Basic functions->Availability check and transfer of requirement>availability check-->define checking groups default value.

mentain the material type e.g HALB plant and availability check.

Also check in OVZ9 checking rule as per your requirement and check mark the required field on the right hand bottom corner.

Hope its useful.

Reward points if useful.