Dear Experts,
I want to scheule my calibration order in QM for calibration of Test Equipment in background.
I have created my maintenance order for calibration of Gauges / Instruments (which are defined as Equipments). The dates for the calibration have been calculated based on time. When I go to the transaction of scheduling the order & save, the inspection lot for calibration is generated & the equipment task list is assigned to the lot.
I want this to automatically happen in background. This is because I have thousands of equipments, for which I can not schedule the calibration manually.
Regards,
Prashant
hi
you can use the IP30 deadline monioting for this purpose,ask your abaper to run the T code in frequent ( Weekly,Fortnight and etc)
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.