Background Scheduling of Calibration Order

Former Member
0 Kudos

Dear Experts,

I want to scheule my calibration order in QM for calibration of Test Equipment in background.

I have created my maintenance order for calibration of Gauges / Instruments (which are defined as Equipments). The dates for the calibration have been calculated based on time. When I go to the transaction of scheduling the order & save, the inspection lot for calibration is generated & the equipment task list is assigned to the lot.

I want this to automatically happen in background. This is because I have thousands of equipments, for which I can not schedule the calibration manually.

Regards,

Prashant

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

you can use the IP30 deadline monioting for this purpose,ask your abaper to run the T code in frequent ( Weekly,Fortnight and etc)

regards

thyagarajan