Hi Gurus,
While creating a project i am getting the error that Project/Wbs no may not be used.
Please help me to sort out this problem.
Helps wl be rewarded.
Regards
rahul
Hi,
Check in Tcode: OPSJ for the particular Project ID whether there a check mark in LKS column.
hope its useful.
Reward points if useful.
thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varshal
I removed all the check marks in both columns but stll same error
Project number or WBS number may not be used
Message no. CJ620
Diagnosis
The key you entered for a project definition or WBS element is not valid according to the settings in Customizing.
System Response
The function was not executed.
Procedure
Check the key entered and the Customizing settings. If the edit has been set, you must enter a project code that corresponds with the current coding mask.
Project number editing
Regards
rahul
Hi,
It seems that you are trying to create the project for which the Project ID is not created hence this is the error.
Try this:
Step 1. Tcode: OPSK remove the check amrk from edit.
Step 2. Remove the check mark from the fiels which were mentioend in earlier replies.
Hope this will solve your issue.
thanks..
Hello,
Please check the coding mask of the project. Transaction OPSJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.