cancel
Showing results for 
Search instead for 
Did you mean: 

No PGI scenario

Former Member
0 Kudos

Hi,

I want to know that ,In which scenario we don't need to do PGI.

Regards

Prabudh

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hello,

As in the earlier replys, if there is a goods movement involved, the PGI needs to be done. Infact, we create a delivery, do the PGI. If physical stock movement not required, no need to doing PGI.

Prase

former_member217082
Active Contributor
0 Kudos

Hi prabudh

When goods are moving physically from the warehouse or storage location then we will be doing PGI .

Example :

While issuing a credit memo to the customer there wont be goods movement but delivery could be there( at times) ,if delivery is there picking qty will be zero .But if delivery is not there then it will be order related billing

Regards

Srinath

Lakshmipathi
Active Contributor
0 Kudos

Dear Prabudh

Wherever physical movement of goods involved, there will be PGI. If goods movement is not there, we dont need PGI

thanks

G. Lakshmipathi

Former Member
0 Kudos

Dear friend,

if PGI involves then its related to delivery otherwise most of the service industry scenario is a non delivery scenario's

regards,

Sudhir