on 05-23-2008 5:57 AM
Hi All,
Can anybody explain and send the conf steps for resource related service contract.
Ex : There should be contract up to a specified period.But they have to raise a bill based on resoure (like labour,material)
utilised.that bill should be periodic.
I hope u can understand the situation,pls reply as soon as possible.
Regards
Swetha
HI swetha,
Your project belongs to?
If its related to service oriented ,then u have to follow these steps for resource related billing.
va01>Cj20n>va02>cat2(Maintain teime shhet)>Cata>DP95>RRB billing.
Revert me if not suitable this to your requirement..
Thanks!!!
Nani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
My project belongs to Construction and Engineering.At site they use material and labour for every activity. AFTER COMPLETION of every activity they need to rise the invoice.
I think it will give the senario. So pls send clear conf steps for me. I am new to this business senario.
Regards
Swetha
Hi,
Your requirement is integration of SD,PS,HR and CO.
Please follow this link.
[Resource related service contract|http://help.sap.com/saphelp_erp60_sp/helpdata/en/05/93fc374e90f23fe10000009b38f8cf/content.htm]
1)Create contract
2)Create WBS element and release it.
3)Create time sheet ,approval,settlement and transferred to CO.(Labor work hours)
4)Execute DP 91
5) Create activity types for each activity (need to take help from PS consultant for confi on material consumed).
6) VF44
7) VF01
Thanks,
Vrajesh