what is Work In Progress in PS

Former Member
0 Kudos

Hi All,

i am doing report for PS module. like finding the Budgect values for perticular Project.

inmy report am using tables like:

PROJ,PRPS,RPSCO,AUFK and AFVC.

here i want to find Work In Progress(WIP) field.

here am not able to find that field.

so where can i find that Field? from what table.

Thanks in Advance.

sudeer.

Edited by: sudeer kumar on May 23, 2008 6:16 AM

Accepted Solutions (0)

Answers (2)

Answers (2)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Table RPSCO, value type 6, 32, 49 gives the values of WIP.

Also table: COBK Business transaction KABG, KABF, KABM gives the required data.

hope its useful.

Reward points if useful.

thanks..

Former Member
0 Kudos

You need to be specific how you classify work in progress, what are you after? $$$ based on RA key calculation?

Mike