kindly explain me what is KANBAN process and where and how to configure the same in SAP, and what is the relation with SD,

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

KANABAN :

The KANBAN method for controlling production and material flow is based on the actual stock quantity in production. Material that is required on a regular basis is continually provided in small quantities in production. Replenishment or the production of a material is only triggered when a higher production level actually requires the material. This replenishment is triggered directly in production using previously maintained master data. The entries you have to make in the system have been reduced to a minimum, for example, the scanning of a bar code. All other actions in the system are carried out automatically in the background.

With KANBAN, the production process controls itself and manual posting is reduced as far as possible. The effect of this is a reduction in lead time and in stock.

In KANBAN, the signal for material replenishment can be triggered, for example, by the work center that requires the material (demand source) by sending a card to the work center that is responsible for manufacturing the material (supply source). This card describes which material is required, the quantity of the material required and where the material is to be delivered. The name KANBAN originally stems from these cards, which are called "kanban" in Japanese. When receiving the material, you can automatically post the goods receipt at the demand source by a further kanban signal by bar code, for example.

The follwing link will be a great reference

http://help.sap.com/saphelp_470/helpdata/en/90/ba63da446711d189420000e829fbbd/frameset.htm

reward points if helpful,

regards,

Amlan Sarkar

Lakshmipathi
Active Contributor
0 Kudos

Dear Sreedhar

Please go thru these links

[PP - KANBAN|http://help.sap.com/saphelp_46c/helpdata/en/cb/7f8aae43b711d189410000e829fbbd/frameset.htm]

[Kanban|https://www.sdn.sap.com/irj/sdn/bpx-automotive?rid=/business_maps/guid/eg1slxvyat1odhrwoi8vzxn3b3jrcgxhy2uuc2fwlmnvbs9zb2nvdmlldy9ty3bnzxquyxnw%0d%0ap3bhy2thz2vpzd0mdmlldz1zbwnyzw5kzxiyjmlkpta4otkwmjzcmzzbrjremdq5qtkzrjhbmdk2%0d%0amzk5qjfgjiz4c2wtymfzzt1odhrwoi8vzxn3b3jrcgxhy2uuc2fwlmnvbs9zb2nvdmlldy9ty3bn%0d%0azxrfbwltzs5hc3a/dxjspxnkbl9uzxcvjiz3zwitdxjspwh0dhbzoi8vzxn3b3jrcgxhy2uuc2fw%0d%0almnvbs9zb2nvdmlldy9ty3bnzxrfbwltzs5hc3a/dxjspsymehnslwxpc3q9c2rux2dlbmvyywxf%0d%0acmvuzgvylnhzbhq7c2rux2xpbmtyzxdyaxrpbmcuehnsddtnzw5lcmf0zuhutuxfu0rolnhzbhqm%0d%0ajnbhy2thz2utawq9jizyzxnvdxjjzxr5cgu9c2rux3nvbhv0aw9ux2nvbxbvc2vyx2z1bgxwywdl%0d%0ajizwyxjlbnrssuq9l3dlymnvbnrlbnqvd2vicgfnzxmvynb4lzqwieluzhvzdhjpzxmvqxv0b21v%0d%0adgl2zs1szxrhawwvu29sdxrpb24gtwfwic0gt0vnjiz0axrszt1lyw5iyw4mjnzpcnr1yww9dhj1%0d%0azq==&prtmode=default]

[KANBAN SCENARIO|http://www50.sap.com/businessmaps/0B1413F015B44089986DF106C5B80C00.htm]

thanks

G. Lakshmipathi

Former Member
0 Kudos

KANABAN :

The KANBAN method for controlling production and material flow is based on the actual stock quantity in production. Material that is required on a regular basis is continually provided in small quantities in production. Replenishment or the production of a material is only triggered when a higher production level actually requires the material. This replenishment is triggered directly in production using previously maintained master data. The entries you have to make in the system have been reduced to a minimum, for example, the scanning of a bar code. All other actions in the system are carried out automatically in the background.

With KANBAN, the production process controls itself and manual posting is reduced as far as possible. The effect of this is a reduction in lead time and in stock.

In KANBAN, the signal for material replenishment can be triggered, for example, by the work center that requires the material (demand source) by sending a card to the work center that is responsible for manufacturing the material (supply source). This card describes which material is required, the quantity of the material required and where the material is to be delivered. The name KANBAN originally stems from these cards, which are called "kanban" in Japanese. When receiving the material, you can automatically post the goods receipt at the demand source by a further kanban signal by bar code, for example.

The follwing link will be a great reference

http://help.sap.com/saphelp_470/helpdata/en/90/ba63da446711d189420000e829fbbd/frameset.htm