on 05-21-2008 9:58 PM
Third Party Sales order is created with delivery date 05/01/08... schedule line is confirmed with delivery date 05/20/08, but the Requisition generated from the Sales Order still uses 05/01/08. Is there a way to change this so that it automatically takes the confirmed date? If so, please advise.
Thanks in advance.
A
Thanks for your response, but my question is - how do I get the date on the Requisition to automatically match the confirmed delivery date on the Sales Order instead of the requested delivery date? I know that when the Req is converted to a PO, it will take the date from the Req, but propose the correct delivery date based on lead-time, etc... but I want the Req itself to have the correct delivery date.
Thanks in advance,
A
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Amanda,
Schedule line depends on delivery lead time. In your case, if requisition is on 05/01/08 only that case you can deliver the goods on 05/20/08 which will involve several sub process like PO, GRN etc. but if you want sale order date = schedule line date then u will have to change delivery lead time.
I hope i answered your query.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.