hi gurus,

Is it possible to have commitment cost raised at the time of creating purchase order and no commitment when purchase requisition is raised?????

If yes, what will be the configuration that needs to be done?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

srinivasan_desingh
Active Participant
0 Kudos

Hi Anjali,

Work around:

1. Dont create PR through project. Create PR manually.

2. Create PO manually and assign to the project manually.

FATMAN

Former Member
0 Kudos

Not possible through standard.

Regards