hi gurus,
Is it possible to have commitment cost raised at the time of creating purchase order and no commitment when purchase requisition is raised?????
If yes, what will be the configuration that needs to be done?
Thanks
Hi Anjali,
Work around:
1. Dont create PR through project. Create PR manually.
2. Create PO manually and assign to the project manually.
FATMAN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Not possible through standard.
Regards
Sreenivas