on 05-21-2008 10:53 AM
We are able to transfer Materails to SRM using standard procedure
But we want to trasnfer Extrenal Material group field values of R/3 material master to SRM
How can we add this specific field while transferring material master to SRM
Regards,
NNK
Hi. I do not think this field exists in SRM, so it may not be possible to replicate it over as standard.
What do you want to use the field for? It might be possible to RFC to get the data at the right time or something.
Regards,
Dave.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks for the suggestion. We are thinking on the same as a alternate.
We want to use think field for Vendor list creation which has specific logic link to this field. We can't use Material group of R/3 as that is already getting used for different purpose in R/3.
So we are looking option to trasfer this field to SRM
Regards,
NNK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.