on 05-21-2008 8:57 AM
Hi
Budget avilablity control with error message at PO level. When Budge is allocated and released, PR is made for less value than budget then when converting to PR to PO it checks properly at budget value and error message delivered. It is happening correct
Where as
*PR is made for more value than budget then when converting to PR to PO it does not check the budget till PO value is within PR value.*
Any increase in PO value checks properly at budget value and error message delivered.
To elaborate my query, following is the exercise I did
If budget check is activated with error message at PO level then :
1) Lets say budget is allocated & release for Rs 100/- for a WBS element
2) PR is made for external activity of network assigned to WBSfor Rs 102 /-, then warning message issued for exceed of budget by Rs 102/-, but PR generated
3) PR copied as value of PO & consistency check done in PO screen then it gives message as "No messages issued during check", now budget is exceeding still no error message
4) Value of PO price will be changed from 102 to 103, then while saving of PO or consistency check of PO, generate error message " Budget is exceeded by Rs 103/-"
5) Now PO price will be changed from 103 to 101, then it gives message as "No messages issued during check", now budget is exceeding still no error message.
Hence with above exercise its observed that once PR warning message is issued, it become basis for PO budget availability check & gives error message if PO value exceed PR value & budget exceeding value will be given equal to amount of actual exceeded value.
Question: What need to be done for checking the budget availability at PO without considering PR value?
Config Doc as below
Budget Profile Business TransGr Action On consuming %
SPLPO ++ (All Transactions) 1 (Warning) 75%
SPLPO 01 ( PO Level) 3 (Error) 100%
SPLPO 03 (Goods withdraw) 3 (Error) 100%
SPLPO 04 (Finan Acco doc) 3 (Error) 100%
JSPLPO (Controlling Doc) 3 (Error) 100%
JSPLPO (Budgeting) 3 (Error) 100%
Regards
Bipin
Hi,
Please implement the Note: 955107.
Am sure this will solve your purpose.
Hope its useful.
Reward points if useful.
thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Bipin,
SAP note 783161 will answer your queries.
Based on same, I suggest put error message at ++ level itself.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This seems standard. Refer the note 124917.
Extract of Note:
When you create a purchase order with reference to a purchase requisition (PReq), the system does not execute any availability control if the order value is smaller or equal to the value of the purchase requisition.
This is also the case if you set in Customizing different tolerance limits or actions for the activity groups purchase requisition and purchase order.
This is not a program error. Since an availability control has already been executed when you create the purchase requisiton, during conversion into a purchase order the system executes only an availability control again if the value assigned increases as a result.
Up to now, it is not planned to change this logic of the availability control in our standard system.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.