the question about date

Former Member
0 Kudos

business scenario:

1, there is a project : A

2, the first layer WBS: A

the secongd layer WBS: A1, A2

the third layer WBS: A11,A12, B21, B22,

the fourth layer WBS: A111 A112 A121 A122 B211 B212 B221 B222 B223

3, Activity assigned to WBS:

now: the same layer WBS's time don't overlap.

and the father WBS's time cover the son WBS's time

and the Activity's time is entirely in the assgined WBS's time.

Please explain me all the steps to be required.

Thanks in advance!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Iam clarifying which i understood from ur question.

You can use topdown Planing or bottom up planning.

In Top down > All activites and the assigned WBS Elelemnts are with in the basic dates of the project defination.

In Bottomup > It will consider all activites and assigned WBS Elelements and will give the basic start and finish date of the project.

Goto Project Defination >control data tab > schdeluing scnario and select the way you required and test it.

Regards

Narayan

Former Member
0 Kudos

the user's demand is:

the lower WBS's time must be in the higer WBS's time.

and activity's time must be in the assigned WBS's time.

Former Member
0 Kudos

You can use Bottom UP scheduling, by which your Activity dates will be taken up by WBS Elements and your lower level WBS Elements Dates will be taken by Higher level WBS Element.