Hi,

I am working on APO version 3.0A. I am trying to change the date range for the macros, i.e. iterations and weeks. I have activated the macro, but that change doesn't have any impact on the result, and when I checked the macro again the date range hasn't been changed.

if anyone has any idea working on this problem in version 3.0A?

I have made this changes in production system itself.

Thanks

Regards

Jignesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Jignesh,

In the poperties for step fo the Macros try the following:

Dont use Automatic Column Adjustment From Column

Dont use Automatic Column Adjustment To Column

Just give From Period and to Period and let it calculat the number of iterations.

Then GENERATE the macro (I assume by saying activating the macro in our query you meant generation as they are separate things in Macro Workbench).

Try this and see if the calculations are fine. I have a doubt that the combination of th checkboxes and iterations is causing the issue.

Regards,

Abhi