I have a problem regarding to the automatic assign of inspection plan. In production I have an inspection plan to control the production of a material, but when certain machine is submitted to a maintenance I should have another inspection plan. Is there a way to define a predefined plan and allow the user to change that inspection plan in some cases?
Thanks in advance,
Tiago MAgalhães
a) Inspection plan for material is defined with Inspection type 04 for production.
Inspection lot is triggered based on the material master defination.
b) Task list is defined for Machine for maintenance. Please discuss with PM Consultant for the processes.
Inspection lot is triggered based on the Maintenance Plan based on ther frequency.
please discuss with PM for further clarification.
with regards,
shridhar.d
9880644496
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There might be two approach for this requirement
Manual
1. You can create multiple inspection plan in one inspection plan group for different machine and assign material to only one inspection plan (one group counter) which you use usually.
2. System will automatically assign inspection plan to inspection lot if you observed that particular machine is in maintenance, you can manually assign inspection plan using QA02 transaction.
Automatic
You can have mutiple inspecion plan assigned to material and create one custom program which will check all the inspection lot created on the basis of certain criteria and will check the machine status if it is in maintenance, program change the inspection plan with apprpriate inspection plan.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.