Dear Sir,
I am facing a problem in my one WBS of project that when i am seeing the assign amount in cj30 it is looking three times of my current budget but another reports like cje0 & ALR. reports it is seeing perfect value i can't understand how it's can happened.
Pls. advice.
Regards,
Vishal Kr. Sharma
Query resolved now..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
According to the SAP Performance assitant:
"Assigned consists of commitment and actual postings. In PS, it also includes plan values of assigned networks and orders."
so when you are in Tcode CJ30 goto EXtras>Availability control->Analysis.
this will help you understand the Assigned budget.
I will sugrest to Run Tcode:CJEN in case you have changed the AVAC settings after allocating the budget.
hope its useful.
Reward points if useful..
thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
The assignment amount usually comes from PO or PR. Pl. check if the PO value is more. If the PO value is more that means u have not activated the availability control.
When u will do MIRO and there is some Project charges , the project charges get added in the assignment value.
Pl. check this scenario.
Regards,
A. Bose
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.