Assign budget is three time of overall Budget in T-code CJ30

Former Member
0 Kudos

Dear Sir,

I am facing a problem in my one WBS of project that when i am seeing the assign amount in cj30 it is looking three times of my current budget but another reports like cje0 & ALR. reports it is seeing perfect value i can't understand how it's can happened.

Pls. advice.

Regards,

Vishal Kr. Sharma

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Query resolved now..

varshal_kachole3
Active Contributor
0 Kudos

Hi,

According to the SAP Performance assitant:

"Assigned consists of commitment and actual postings. In PS, it also includes plan values of assigned networks and orders."

so when you are in Tcode CJ30 goto EXtras>Availability control->Analysis.

this will help you understand the Assigned budget.

I will sugrest to Run Tcode:CJEN in case you have changed the AVAC settings after allocating the budget.

hope its useful.

Reward points if useful..

thanks..

Former Member
0 Kudos

hi,

The assignment amount usually comes from PO or PR. Pl. check if the PO value is more. If the PO value is more that means u have not activated the availability control.

When u will do MIRO and there is some Project charges , the project charges get added in the assignment value.

Pl. check this scenario.

Regards,

A. Bose