on 05-20-2008 1:16 PM
Hi
I have a confusion in transporting the PA DS from D - Q - P systems. this is for DP PA backup. They have many tabs in DP/SNP extraction.
I generated the DS in D system. Then my next step should be Replicate DS. Should i click 'Transport DS' ?
Once i replicate, and in BW side, i will replicate the Metadata. then its fine within that system. Now how do i tpt this DS from D to Q and P systems ?
Do i have to create this DS manually in all systems and replicate individually or should i tpt all in a tpt itself ?
Can anyone pls give me the step by step process ?
Secondly, i dont have same appln comp hierarchy in all 3 systems. I think thats still ok to tpt ?
thx
venkat
closing this thread.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Harish
I actually tried that option in the first option. The tpt was failed in Q system. It says "Program terminated (job: RDDEXECL, no.: 12272400)' and the job log says
Step 001 started (program RDDEXECL, variant , user ID DDIC)
All DB buffers of application server sapbwq were synchronized
ABAP/4 processor: ASSERTION_FAILED
Job cancelled.
So i am getting many doubts, like do i have to manually click the tab in PA ext tools, Transport DS to tpt it to other systems ?
and it also says "Application component DM of DataSource 9AZXXXXXX does not exist" when i click "check Datasource" tab. This DM is existing in D system but not in Q, P systems. But i have other DSs working fine under NODESNOTCONNECTED AC.
Any advice pls..
thx
venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinidhi
Thx for your suggestion. But we are already in Prodn. PAs are in P system already. I dont want to use TSOBJ again just to tpt the DS.
I am creating a new DS and this one i want to tpt to Q/P systems. I have a big doubt in the data extraction tools - about the tab : Transport DS. Should we use this (from PA scrn) to create a tpt or manually create a tpt from BW side ? and import into Q/P systems ?
need help in this.. I also have problems in this DS area.
thx
venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You may transport your planning area using manual option /SAPAPO/TSOBJ and then choose the checkbox 'With datasource transport' for the selected planning area. This will enable you to transport your PA datasource from D to Q & P systems.
regards,
Srinidhi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.