While Seeing the profit Centre reports the following Message appears.

The environment for operating concern S001 either has not been generated or is inconsistent.

_System Response

The transaction was cancelled.

Procedure

You cannot use an operating concern until you have activated the data structures and generated the environment.

Execute the transaction Maintain operating concern and display the status. There the system displays a list of the actions that have yet to be carried out.

If you do not have authorization to do this, contact your system

administrator._

Please advice what is to be done.

regards,

Amlan Sarkar

Accepted Solutions (1)

Accepted Solutions (1)

sridhar_muthekepalli3
Active Contributor
0 Kudos

Hi:

Operating concern was not activated or defined.

The FICO Consultant has to configure the Profitability analysis or COPA, if you want to see the profit center reports.

Please let me know if you need more information.

Assign points if useful.

Regards

Sridhar M

Former Member
0 Kudos

Dear Sridhar,

I have Checked the SIS Updating For S001

Please give me more details...

regards,

Amlan Sarkar

Email on the Bussiness Card.

9867176451

Answers (3)

Answers (3)

Former Member
0 Kudos

answered

sridhar_muthekepalli3
Active Contributor
0 Kudos

Hi:

Can you give more details.give me the t.code whcih you are using.

Regards

Sridhar M

Former Member
0 Kudos

hi check operating concern setting

KEP8: Define Operating Concern

Path: IMG ->Definition ->Controlling-->Create Operating Concern