on 05-20-2008 7:48 AM
Hi gurus,
recently i faced a question.The output of DP is demand Plan..Then,what is the output of SNP?
Thanks in Advance..
Regards..
Yogi..
Dear Yoganand
SNP is a bucketed ,medium term, cross plant planning process.
As the output of SNP, Planned orders, purchase requistions and stock transport requistions are transferred to OLTP systems so that the medium to long term plans are available.
Hope this clarifies your doubt.
Regards
Nav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Supply Plan!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It is Medium term- Production and distribution plan
regards
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.