on 05-20-2008 7:05 AM
Hi,
At present scenario my client has one single cost, but going forward they want to split this into fixed & variable. In OKG2 RA cost elements has been defined as of now. Going forward i will have two cost elements (say for against Valuated Actual Cost, Calculated Cost etc) one for fixed and one for variable.
Can any one advice how can i do my configuration for RA.
Regards
Sreekanth
Hi,
As per my understanding what you are looking for is to split the cost into various catagories. This can be achieved as-
1. Create the line IDs as production cost, overheads...etc. in (SPRO-Revene and EaringsRA)
2. Then map these line IDs against respective cost elements in OKG5.
3. Map these line ID with RA key in OKG4
Based on the mapping done in step 3, you can create the PA structure and assign the value fields to specific cost elements used in step 3.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.