on 05-19-2008 11:52 AM
Hi friends,
We created materials reservation in PS WBS through execution services, but the default movement is 221.
I would like to have the possibility to choose between movement 221 and 415 during creation of the reservation in PS, it is that possible?
Thank you.
Regards,
Tiago Ferreira
Hi,
Try it with T code OPT1. Here you can maintain the default movement types
Thanks