on 05-19-2008 11:01 AM
Hi Friends,
This is Bhaskar, we have ECC 6.0, DB2, AIX. Transport Request is taking long time while import into Production. Every time it shows Lorry Symbol(Import is running). Please help me out, how to resolve the issue.
Thanks a lot,
Bhaskar.
Hi,
I faced the same error in my previous case.
The problem for me is that i gave asynchronous mode for importing. So try this one, while importing, in that import options change the synchronous and asynchronous mode. I hope this will work for you.
Regardrs
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi juan,
I said that this is the problem which i faced earlier in my case.
In my case i transported the objects between two domains. But its showed an transport symbol for a very long time. As a trick we just checked by changing the mode and reimported the request. As simple as such its worked for me and all the objects also came top the target system in my case.
Regards
Vijay kumar
check the logs and the tp monitor to see the status of the transport, then take actions (or not) accordingly.
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
24 | |
11 | |
9 | |
7 | |
5 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.