on 05-19-2008 7:38 AM
Hi,
I confirmed an activitys as follows:
1. Switch to Gantt Chart screen
2. Choose an activity
3. click confirm button to open confirm dialog
4. input 30% and click back button to go back Gantt chart screen
on the Gantt Chart I cannot recognize if this activity was already confirmed. How to see this?
Please help!
Long Nguyen,
Hi,
Upon confirming the activity Save the project.
Reopen the project in gantt chart.
Goto:
Settings>Field selection>(Remove unwanted Fields)--> On the right hand side field selection choose
1. status,
2. Processing % of dur. and
3. Processing % of work and move it in the left hand side (selected fields)
Adjust the length of these two fields to see the data clearly (e.g. 10)
And hit enter.
You should be able to see the status as MCNF,PCNF and in the % coolum the Degree if processing in your cse 30%
Hope its useful.
Reward poits if useful.
Thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.