on 05-18-2008 1:15 PM
Dear PS friends,
I have an issue in order plan cost updation ( budget report ).
Used the prescribed WBS in maintenance order ( additional data ), but its not appearing in planned cost of CJ31 screen.
Checked the following
a) WBS is account assignment element.
b) Network type order appended indicator in OPSV.
c) Setting in network type parameters for " determine plan
cost".
d) WBS and order - both are showing plan cost when booked separately, but not integrated.
Can anybody help me to resolve this !
Thanks in advance
-- Sri --
Edited by: Srinivasan Madaswamy on May 18, 2008 2:15 PM
Hi,
In OPSV, ensure that both check boxes are ticked for Maintenance Order, ie order category 30.
Hope this helps.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In case of the maintenance order (Order Category:30)
Please check the follwoing in Tcode OPSV:
1. type is maintained default i.e ++++ (this will consider all the order types mantioned for maintenance order.
2. Please selelct the appropriate controlling area.
3. Appended plan indicator has to be checked mark,
4. Assigned funds in the plan indicator has to be checked mark,
5. In Tcode IW32: In the additional data Tab assign the WBS Element. Save the maintenance order.
Hope its useful.
Reward point if useful. Revert abck if any other issue.
Thanks..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Varshal,
All the settings were checked and found intact. No issues !
I could able to locate the issue with the user exit used for controlling the allocation of WBS automatically for this order type.
Thanks for your valuable input which really helped me to analyse and kill the issue
Regards
Srinivasan
Hi,
I assume you are talking about the order as Network :Order category 20.
For this:
Please check the following:
1. Mainatain the costing variant in Tcode: OPL1
2. Assign the Valuation variant to the above costing variant.
3. Maintain the strategies for the various tabs inside the valuation variant.
4. Maintian the cosing variant from step 1 in Tcode: OPUV.
Hope it helps,
Reward points if useful. Revert back if any other issue.
Thanks...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.