business scenario:
1, The sole purpose is to capture costs, use KB21N for activity allocation.
Question: in WBS or netwok activity. there is no relevant work time.
Please explain me all the steps to be required.
Thanks in advance
Hi,
I under stood as follows.
You want to capture actual cost in PS. For this you need to have Work centers.
Assign the same to internal actvities. Release the activity and confirm the same.
In SAP, Standard report, you get No hours Actuals, Planed... etc. Check in CN41, CN71 and execute the Project. Check the field selection, there you get the details you required.
Hope my understanding is correct.
Regards
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can run KB21N for wbs, no need for networks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.