on 05-16-2008 2:43 PM
Hello,
The scenario is Bom A has A1, A2 and A3 as its child componnents. A2 is again a sub assembly with A21,A22 and A23 as child parts.
A2 is a phantom assembly. Requiremnts for its child parts should get generated but no planned order is required for A2 as it is phantom assembly.
In Material Master of A2 (phantom assembly) =, following settings are maintained.
1) MRP type = PD.
2) Procurement Type = E.
3) Special Procurement = 50 (Phantom assembly).
4) Stratergy Group = 50 (Planning with out final assembly) are maintained.
When we assign BOM A to project activity and run MRP, Planned order for A2 is also getting generated. Which should not as it is maintained as Phantom assembly.
Kindly advise if any additional settings are required to make it work.
Thanks
Saikishore Ganga.
Hi ;
check the following:
SPRO>Production->Basic data->Item Data->Define explosion type
Check whats the setting for the Switch off phantom assembly.
hope its useful.
Reward points if found useful.
thanks...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.